The Phase I bond projects began February 1, 2010.
Phase I consisted of 17 projects that included replacement of playgrounds, fencing and field repairs and the construction of two new recreation centers, replacing older buildings. Phase II consisted of 6 projects that included new gymnasium, new adult activity center and technology center, new administrative office, replacement of lighting on tennis courts and 3 press boxes with canteen and storage areas.
Monthly Bond Update Report 6.16.2014
Phase III is well underway.
Phase I Construction List



Proposed Scope of Work: New recreation center, new gymnasium, new swimming pool, new parking lot, replace outdoor restrooms; Completed June 2012
Proposed Scope of Work: Replace field fencing, replace outdoor restrooms, upgrade racquetball courts; Completed Summer 2011







Proposed Scope of Work: Replacing field fencing, replacing field lighting, replacing field irrigation; Completed Fall 2010
Proposed Scope of Work: New playground equipment, upgrade racquetball courts, replacing field irrigation; Completed Summer 2011



Phase I consisted of 17 projects that included replacement of playgrounds, fencing and field repairs and the construction of two new recreation centers, replacing older buildings. Phase II consisted of 6 projects that included new gymnasium, new adult activity center and technology center, new administrative office, replacement of lighting on tennis courts and 3 press boxes with canteen and storage areas.
Monthly Bond Update Report 6.16.2014 [1]
Phase III is well underway.
[1] http://richlandcountyrecreation.com/wordpress/wp-content/uploads/2014/06/Bond-Report-2014-06-16.pdf
Phase II Construction List


Proposed Scope of Work: 4 soccer fields, 1 baseball field with press box, walking trail (approx. 1/2 mile), 2 commercial well systems with VFD, irrigation on all fields, parking; Anticipated Completion: Spring 2013



Phase I consisted of 17 projects that included replacement of playgrounds, fencing and field repairs and the construction of two new recreation centers, replacing older buildings. Phase II consisted of 6 projects that included new gymnasium, new adult activity center and technology center, new administrative office, replacement of lighting on tennis courts and 3 press boxes with canteen and storage areas.
Monthly Bond Update Report 6.16.2014 [1]
Phase III is well underway.
[1] http://richlandcountyrecreation.com/wordpress/wp-content/uploads/2014/06/Bond-Report-2014-06-16.pdf
Phase III Construction List
Scope of Work: New outdoor restrooms, lights on tennis courts, fencing, parking and demolition. Completed, but some changes were made
Proposed scope of work: New mini neighborhood park. PENDING






Proposed scope of work: (4) mini neighborhood parks. PENDING

Proposed scope of work: New mini neighborhood park. PENDING
Proposed scope of work: New swimming pool with office, restrooms, dressing rooms and lockers. Completed June 2014
Phase I consisted of 17 projects that included replacement of playgrounds, fencing and field repairs and the construction of two new recreation centers, replacing older buildings. Phase II consisted of 6 projects that included new gymnasium, new adult activity center and technology center, new administrative office, replacement of lighting on tennis courts and 3 press boxes with canteen and storage areas.
Monthly Bond Update Report 6.16.2014 [1]
Phase III is well underway.
[1] http://richlandcountyrecreation.com/wordpress/wp-content/uploads/2014/06/Bond-Report-2014-06-16.pdf