Phase I consisted of 17 projects that included replacement of playgrounds, fencing and field repairs and the construction of two new recreation centers, replacing older buildings. Phase I is nearing completion.
Monthly Bond Update Report 05.20.2013
Phase II is well underway.
Proposed Scope of Work: New recreation center, new gymnasium, new parking lot, replace field fencing; Completed August 2012
Proposed Scope of Work: New community center, new parking lot, new playground equipment, replace field fencing, replace field lighting; Completed January 2012
Proposed Scope of Work: New parking lot, new stairs, replace outdoor restrooms, replace field fencing, replace field irrigation; Completed Fall 2011
Proposed Scope of Work: New recreation center, new gymnasium, new swimming pool, new parking lot, replace outdoor restrooms; Completed June 2012
Proposed Scope of Work: New playground equipment, replace field irrigation; Completed Summer 2011
Proposed Scope of Work: New tennis pro shop ; Completed April 2011
Proposed Scope of Work: Replace field fencing, new picnic shelter; Completed Summer 2011
Proposed Scope of Work: New playground equipment, upgrade racquetball court; Completed Summer 2011
Proposed Scope of Work: New playground equipment; Completed Summer 2010
Proposed Scope of Work: New playground equipment; Completed Summer 2010
Proposed Scope of Work: New playground equipment; Completed Summer 2010
Proposed Scope of Work: New playground equipment, upgrade racquetball courts, replacing field irrigation; Completed Summer 2011
Proposed Scope of Work: Replace field fencing, replacing outdoor restrooms; Completed Summer 2011
Proposed Scope of Work: Replace Field Fencing; Completed Fall 2010
Proposed Scope of Work: Replace Field Fencing; Completed Fall 2010
Proposed Scope of Work: New gymnasium; Completed December 2012
Proposed Scope of Work: 3 press boxes with canteen and storage areas; Completed March 2012