The Phase I bond projects began February 1, 2010.

Phase I consisted of 17 projects that included replacement of playgrounds, fencing and field repairs and the construction of two new recreation centers, replacing older buildings.  Phase I is nearing completion.

Monthly Bond Update Report 05.20.2013

Phase II is well underway.


Phase I Construction List

BRP-Prk1Proposed Scope of Work: New recreation center, new gymnasium, new parking lot, replace field fencing; Completed August 2012
IMG_0044Proposed Scope of Work: New community center, new parking lot, new playground equipment, replace field fencing, replace field lighting; Completed January 2012
New 2 030Proposed Scope of Work: New parking lot, new stairs, replace outdoor restrooms, replace field fencing, replace field irrigation; Completed Fall 2011
IMG_4513Proposed Scope of Work: New recreation center, new gymnasium, new swimming pool, new parking lot, replace outdoor restrooms;  Completed June 2012
Proposed Scope of Work: Replace field fencing, replace outdoor restrooms, upgrade racquetball courts; Completed Summer 2011
IMG_8058Proposed Scope of Work: New playground equipment, replace field irrigation; Completed Summer 2011
rctc01Proposed Scope of Work: New tennis pro shop ; Completed April 2011  
Bond 2008 034Proposed Scope of Work: Replace field fencing, new picnic shelter; Completed Summer 2011
Friarsgate 05-04-10 006Proposed Scope of Work: New playground equipment, upgrade racquetball court; Completed Summer 2011
IMG_0597Proposed Scope of Work: New playground equipment; Completed Summer 2010
RCRC Photos 010Proposed Scope of Work: New playground equipment; Completed Summer 2010
IMG_8099Proposed Scope of Work: New playground equipment; Completed Summer 2010
Proposed Scope of Work: Replacing field fencing, replacing field lighting, replacing field irrigation; Completed Fall 2010
NSP Playground 2010-03-31 001Proposed Scope of Work: New playground equipment, upgrade racquetball courts, replacing field irrigation; Completed Summer 2011
New 020Proposed Scope of Work: Replace field fencing, replacing outdoor restrooms;  Completed Summer 2011
new 042Proposed Scope of Work: Replace Field Fencing;  Completed Fall 2010
Trenholm Fence 006Proposed Scope of Work: Replace Field Fencing; Completed Fall 2010
Phase I consisted of 17 projects that included replacement of playgrounds, fencing and field repairs and the construction of two new recreation centers, replacing older buildings.  Phase I is nearing completion. Monthly Bond Update Report 05.20.2013 [1] Phase II is well underway. [1] http://richlandcountyrecreation.com/wordpress/wp-content/uploads/2013/05/Bond-Report-2013-05-20.pdf

Phase II Construction List

IMG_2616aProposed Scope of Work: New  gymnasium;  Completed December 2012
Proposed Scope of Work: New adult activity center, new technology center; Anticipated Completion: Spring 2013
Proposed Scope of Work: 4 soccer fields, 1 baseball field with press box, walking trail (approx. 1/2 mile), 2 commercial well systems with VFD, irrigation on all fields, parking; Anticipated Completion: Spring 2013
Pkg2AProposed Scope of Work: 3 press boxes with canteen and storage areas; Completed March 2012
Proposed Scope of Work: 2 new lighted tennis courts; Anticipated Completion: Fall 2012
Proposed Scope of Work: New headquarters building, new maintenance building; Anticipated Completion: Spring 2013